0

Embankment Meaning:

The earthen material, which is get laid and compacted to raise the grade line of a proposed highway or railway above the original ground level of the existing ground, is called embankment. The grade line of the road may be raised due to some reasons which are as follows:

  • keeping subgrade above Ground Water Table(GWT)
  • preventing damage of pavement from the surface and capillary water. 
  • To maintain the designed vertical alignment of the road.

Embankment design considerations include filling height, the material used, settlement consideration and stability analysis. In case of grater fill height and weak foundation soil, ground improvement is necessary to control the settlement of the foundation soil. After construction due to consolidation or fill height settlement, or both the embankment may settle.

Embankment Settlement :

  • When embankment foundation consists of compressible soil with high moisture content
  • Due to inadequate compaction of filled layers during construction operation

Action Measure:

The following action can be taken to eliminate the risk of settlement during construction operation.

  • To increase the rate of consolidation of foundation soil by providing sand drain.
  • By proper compaction of filled layers during construction operation

Embankment Construction Equipment:

  • Excavator
  • Tippers /Dumpers
  • Motor Graders
  • Vibratory Compactor
  • Tractors Dozer with Disc Harrows/ Spreading Blade / Ploughs
  • Water Bowser with Sprinklers etc.
  • Crawler Dozers

Construction Material:

  • The material shall be soil, moorum and gravel, fly ash or a mixture of these three.
  • The material shall satisfy the requirements defined in the clauses of the contract document. 
  • The materials used in the works shall be suitable roadway/drainage/structure excavated material or borrowed material approved by the Engineer as per requirements of MORTH Specifications. 
Embankment-Material

Material Properties:

  • MDD: 1.52 T/Cum for embankment up to 3.0m height, 1.60 T/Cum for embankment more than 3.0m height. For fly ash, separate density requirement as per contract shall be applicable.
  • CBR:  Minimum CBR requirement NIL   
  • Coarse material: Size not more than 75mm
  • Free swell index: Not exceeding 50% (to be used only below 500mm of top of the embankment)   
  • Liquid Limit: Not exceeding 70 
  • Plasticity Index: Not exceeding 45 

Setting out Works:

  • The Centerline of the road shall be set out by means of continuous transit theodolite/total station survey.
  • The reference points for this shall be as per the project drawings and instruction of the Engineer.
  • The working Bench Marks shall be established from the approved reference benchmarks and also near to all cross drainage structures.
  • The reference points shall be so located that these shall not be disturbed during construction.
  • Reference pegs shall be fixed on both sides of the slopes. These pegs are meant as guides and shall be about 0.50-1.50m away from the toe of the embankment.
  • Mark the limits of embankment fill with lime powder or pegs on the ground, after clearing, and grubbing is completed.

Embankment Construction:

  • Atterberg limits, MDD, OMC, and in-situ dry density of the material at ground level shall be checked. 
  • Any unsuitable material shall be removed as directed by the Engineer and replaced with suitable material.
  • Embankment may be constructed by laying suitable material in layers not exceeding 250mm thickness.
  • Each layer is compacted by rolling to a satisfactory degree or to the required density before the next layer is placed. 
  • Compaction is carried out at optimum moisture content so as to take benefit of maximum dry density using a specified compacting effort and equipment.
  • All the measurement of filling shall be taken at every stage of construction.

Quality Control and Testing:

  • The compaction control shall be achieved on each layer by taking a random measurement of density as specified CL.903.2.2 in the MORTH specifications.
  • Field density tests shall be conducted by sand replacement method/Non Destructive tests (Nuclear density gauge method).
  • When density measurement reveals any soft areas in the embankment, these are compacted further. If in spite of that the specified compaction is not achieved, the material in the soft area shall be removed and replaced by approved material, compacted to the specification.
  • Test results shall be entered in the relevant inspection/test formats and as per respective approved inspection and test plans.    
  • The alignment and levels of the compacted embankment top layer shall be checked to confirm that these are within permissible limits as specified in Table 900-1.
  • Record of testing shall be maintained in pictorial/chart form showing the details like date of testing, bore area used, log no. of approval request etc. as necessary to monitor the activity.
  • The following tests are Pertinent to Embankment (Ref Cl. 903.2 of MORT&H)
Sr. NoTestCodeFrequency
1Sand ContentIS: 2720
(Part – 4)
Two tests per 3000 cum
2Plasticity testIS: 2720
(Part – 5)
Each type, two tests per 3000 cum
3Density testIS: 2720
(Part – 8)
Two tests per 3000 cum subject to a minimum of one test per 1000 Sqm.
4Deleterious contentIS: 2720
(Part – 27)
Engineer to decide
5Moisture ContentIS: 2720 (Part – 2)One test per 250 cum.

Your Opinion Matters: How easy is it to understand the information on our website?

View Results

Loading ... Loading ...
0
Summary
Embankment Meaning - Construction - Quality Control
Article Name
Embankment Meaning - Construction - Quality Control
Description
The earthen material, which is get laid and compacted to raise the grade line of a proposed highway or railway above the original ground level of the existing ground, is called embankment.
Author
Publisher Name
Construction Civil
Publisher Logo

WhiteHelmet

ConstructionCivil is a learning platform for all the Civil Engineers and Civil Engineering Students throughout the world. I have started this Website to educate and keep people notified by forming a trusted source of knowledge, everything related to Civil/Construction Engineering.
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments